City Projects
City Projects
MAP DETAILS
-
Verdine Water Plant Phase 3-Upgrading of Systems (WP20-1)
Verdine Water Plant upgrading of systems. Engineer: Meyer & Associates. Contractor: TBD. Cost Estimate: $5,515,750. Bid Date: TBD. Start Date: TBD. Funding Source: Capital/Water Sector. -
Wastewater Plant Renovation/Replacement of Sludge Digester No. 2 System (SP19-4)
Renovation/replacement of sludge digester No. 2 system at Wastewater Plant. Engineer: Meyer & Associates. Contractor: TBD. Cost Estimate: $300,000. Bid Date: TBD. Start Date: TBD. Funding Source: Capital/FEMA. -
Wastewater Plant Automated Septage Receiving (SP19-3)
Counter for sewage that is processed at the Waste facility. Engineer: Meyer & Associates. Contractor: TBD. Estimate: $1,500,000. Bid Date: TBD. Start Date: TBD. Funding Source: Capital. -
ST22-2- Concrete Rehab
Rehab of concrete streets Phillips, Leland, and Taylor. Engineer: Lancon. Contractor: TBA. Cost Estimate: 2,600,000. Bid Date: TBD. Start Date: TBD. Funding Source: Capital. -
LS19-3 - Prater Road/ Bayou D'Inde Lift Station Improvements
Rehab of sewer lift station and further movement into City easement. Engineer: Meyer & Associates. Contractor: TBA. Cost Estimate: $750,000. Bid Date: TBD. Start Date: TBD. Funding Source: Bond/ American Recovery Act. -
LS19-8 Sulphur Hwy 90 Sewer Lift Station Improvements
Improvements and relocation of Hwy 90 lift station. Engineer: Meyer & Associates. Contractor: TBD. Cost Estimate: $580,000. Bid Date: TBD. Start Date: TBD. Funding Source: Capital/Bond/ American Recovery Act. -
ST22-3 2021/2022 Overlay
Rehab of asphalt streets. Engineer: Meyer & Associates. Contractor: TBA. Cost Estimate: $500,000. Bid Date: TBD. Start Date: TBD. Funding Source: Capital. -
MPLSPS - Maplewood and Maplefork Sewer Pump Station Improvements.
Repair of Pump Station. Engineer: Meyer & Associates. Contractor: TBA. Cost Estimate: $2,400,000. Bid Date: TBD. Start Date: TBD. Funding Source : Capital. -
Burton Street Reconstruction-Beglis to Savoy (BURTON)
Reconstruction of Burton Road from Beglis to Savoy. Engineer: Meyer & Associates. Contractor: TBD. Cost Estimate: $1,200.000. Bid Date: TBD. Start Date: TBD. Funding Source: Bond. -
Wastewater Plant-SBR Basin Improvements-Phase I (SP22-1)
SBR Basin Improvements Phase I. Engineer: Meyer & Associates. Contractor: The Lemoine Company. Bid Award: $880,900. Start Date: Apr-22. Est. Completion Date: Feb-22. Funding Source: Capital/FEMA -
WPVERD - Verdine Water Plant New North Well Replacement No. 13- Completed
Engineer: Meyer & Associates. Contractor: Layne Christensen Company. Scope of Work: New well due to old well collapsing. Bid Award: $1,518,425. Start Date: September 2021. Est. Completion Date: August 2022. Funding Source: Capital.
WPVERD - Water Well No. 13 - Capital Project Update -
DRAN17- Crocker Street Water Line Replacement/ Relocation- Completed
Replacement and Relocation of water line on W. Crocker Street. Contractor: MPB Construction. Cost Estimate: $178,000. Start Date: February 2022. Completion Date: June 2022. Funding Source: Capital.
DRAN17 - Crocker Street Water Line Replacement -
Roselawn Cemetery Fencing (CP22-3) - Completed
Repair of fencing around cemetery. Engineer: Meyer & Associates. Contractor: A-1 American Fence, Inc. Bid Award: $176,498. Start Date: August 2022. Est. Completion Date: March 2023. Funding source: Capital/FEMA.
CP22-3 - Roselawn Cemetery Fencing -100 percent -
Mimosa Heights Street Improvements Phase 2-Street Rehab (ST19-1)- Completed
Reconstruction of W. Mimosa, S. Mimosa and Morgan. Engineer: Meyer & Associates. Contractor: Williams Equipment Services LLC. Bid Award: $439,389. Start Date: Jun-22. Est. Completion Date: Nov-22. Funding Source: Capital.
ST19-1 - Mimosa Height Improvements - Phase 2 -100% -
Smith Road and Archie Raod Rehabilitation (ST20-1) - Completed
Repair Smith Road and Archie Road. Engineer: Meyer & Associates. Contractor: Williams Equipment Services. Bid Award: $447,877.76. Start Date: Aug-21. Completion Date: Aug-22. Funding Source: Capital.
ST20-1 - Smith/Archie Road Rehabilitation -
WP22-3 - North Water Treatment Improvement Program - Removal and Replacement of Pressure Filters
Removal and Replacement of Pressure Filters. Engineer: Meyer & Associates Inc; Contractor: The Lemoine Company, LLC; Bid Award: $3,473,620.00; Start Date: TBA; Est. Completion Date: TBA ; Funding Source: Water Sector Grant
North Water Plant - 0 percent completion -
SP23-1 - Operations & Maintenance Emergency Repairs & Control System Improvements Regional Wastewater Treatment Facility Ultraviolet Disinfection System
Full refurbishment and upgrades to the existing WWTF Ultraviolet (UV) Disinfection System. Engineer: Meyer & Associates. Contractor: Coastal Process, LLC. Bid Award: $651,025.00. Start Date: TBA Est. Completion Date: TBA. Funding Source: Capital.
SP23-1 - UV Light System for Disinfection - 40% -
ST24-1 - 2023 Pavement Markings
Repainting of school crossings. Engineer: Meyer & Associates Inc. Contractor: Nation Services Company Inc., Bid Award:$179,770.00, Start Date: October 2023, Est. Completion Date: December 2023, Funding Source: Capital
ST24-1 - 2023 Pavement Markings - 0 percent -
CPSPD - Sulphur Law Enforcement Center Hurricane Laura Repairs
Repair of building from damage sustained from Hurricane Laura. Engineer: Meyer & Associates Inc.; Contractor: Pat Williams Construction, LLC; Bid Award:1,370,278.00; Start Date: 5/1/2023; Est. Completion Date: 10/28/2023; Funding Source: FEMA/ Capital
CPSPD - Law Enforcement Center - 50 percent -
Housing Authority Sanitary Sewer Lift Station Improvements (LS19-12)
Improvements to Lift Station located in the Sulphur Housing Authority location. Engineer: Meyer & Associates. Contractor: MPB Construction, LLC. Bid Award Amount: $625,457. Bid Date: August 2022. Start Date: October 2022. Funding Source: Capital/American Recovery Act.
LS1912 - Housing Authority Lift Station Improvements - 75 percent -
Maplewood Drive Rehab Phase II
Reconstruction of Road between Post Oak - E. Diane Street. Engineer: Meyer & Associates. Contractor: Williams Equipment Services LLC. Cost Estimate $4,402,829.30. Start Date: Feb-22. Est. completion Date: Aug-23. Funding Source: Capital/Capital Outlay.
MPWOOD - Maplewood Drive - Phase 2 - 100 % -
Post Oak Road-Aubrianna to Burton (ST20-2)
Rehab of Post Oak Road from Aubrianna to Burton. Engineer: Meyer & Associates. Contractor: Prairie Contractors, LLC. Bid Award Amount $4,143,343.92. Start Date: 7/10/2023, Est. Completion Date: 10/28/2023 Funding Source: Capital/TIP
Post Oak Road - 5 percent -
ST22-1 - Tillman, Brandi, Ashley Rehabilition
Rehab of Brandi, Tillman and Ashley Streets. Engineer: Meyer & Associates. Contractor: Williams Equipment Services, LLC. Bid Award: $1,637,000.34. Start Date: October 2022. Est. Completion Date: August 2023. Funding Source: Capital
ST22-1 - Brandi Tillman, and Ashley Rehabilitation -95% -
Henning Drive/Weekly Road-LA1256 to LA27 (T_HNDR)
Repair of Henning/Weekly Road-LA1256 to LA27. Engineer: Meyer & Associates. Contractor: R. E. Heidt Construction, LLC Bid Award: $1,411,972.09. Bid Date: August 10, 2022. Start Date:5/24/2023; Est. Completion Date: 8/22/2023 Funding Source: Capital/TIP
Henning Drive / Weekly Road -100 percent